Australia spent billions on jet fighters off the plan. Now, we're having trouble even flying them

  • Written by: Peter Layton, Visiting Fellow Griffith Asia Institute, Griffith University

There’s a problem with Australia’s brand new fighter jet – it’s just not that reliable. As a result, it flies about 25% less than it should. Less flying means fewer well-trained pilots, but it also hints at other problems lurking in the background.

Everybody who buys a house or apartment off the plan knows there may be some surprises along the way. Australia’s fighter jets are the same.

Why Australia bought these jets

Australia committed to its new F-35 fighters off the plan in 2002. At the time, the F-35 was still a twinkle in the eyes of Lockheed Martin’s marketers. The US and several European countries had commissioned the aerospace company to design, build and manufacture the F-35, with the first step being a prototype.

Australia’s plan was to buy four squadrons – about 72 jets in total – at a cost of around A$16 billion. The F-35 was intended to replace the air force’s ageing Hornet fighters and F-111 bombers. And back in 2002, when Middle East wars were raging, a short-range stealth fighter seemed more than adequate.

But by 2010, with China firmly on the rise, it became apparent this was a poor strategy. In retrospect, a key error was looking at the F-35 simply as a replacement aircraft without first assessing the changing strategic environment. But by then, too much money had been sunk into the F-35 program to change course.

Then, the F-35 development ran late, and the first tranches of Australia’s fleet weren’t ready to be deployed on operations until December 2020.

Scott Morrison inside an F-35 fighter jet.
Prime Minister Scott Morrison during a ceremony to welcome the fifth-generation F-35 fighter jets to BAE Systems Australia near Newcastle. Darren Pateman/AAP

Escalating problems

Building the aircraft proved harder than anticipated and this inexorably fed into higher costs.

Much of the money that should have been spent on building the maintenance support system went into trying to fix the aircraft’s continuing hardware and software problems. Accordingly, there are now fewer depots to fix broken parts and fewer spare parts than there should be.

Little of this is in Australia’s control. America’s global support solution (GSS) is used to keeping Australia’s F-35 fleet flying. The GSS manages spare parts, maintenance, supply chain support, training systems and engineering. But the program is new, creating problems both now and into the next decade.

Read more: What do we need of a military fighter aircraft?

There was a second compounding problem arising from the drawn-out development process: the F-35 jets were constructed at different times over the past ten years in seven different configurations. Think about the maintenance staff having to repair individual aircraft in a large fleet with no single standard configuration. Every repair is an adventure – and a learning experience.

The configuration complexity, insufficient spare parts and slow spare part repair times mean there are fewer serviceable aircraft on the flight line now than was expected even a couple of years ago.

In 2019, the Department of Defence estimated the F-35 fleet would fly 11,800 hours in the fiscal year 2021-22. The real figure, however, is 3,000 hours below that.

In simple terms, Australia is short the flying hours needed to keep a squadron’s worth of pilots combat ready. This is very worrying, as Australia only has three operational F-35 squadrons in total.

Continuous upgrades at tremendous cost

A perfect solution to this is probably not possible. For example, the two F-35 aircraft Australia bought in 2013 for more than A$280 million are now arguably too old to be upgraded to the current configuration. In terms of flying combat missions, these two aircraft are obsolete.

The US Air Force frets its similarly old F-35s are now just crushingly expensive training aircraft.

Most of Australia’s fleet is planned to be upgraded to be broadly similar to the US fleet, although this will cost even more money. It may seem strange to have to pay extra to upgrade a brand new aircraft on delivery, but that’s not the end of the problems. There is another complication.

Australia’s latest F-35s (as well as the upgraded older ones) use the Block 3F software, a digital operating system designed by Lockheed Martin. It is proving to be just as costly to keep updated as the jets themselves.

Lt. Gen. S. Clinton Hinote, the US Air Force’s deputy chief of staff, has serious concerns about the outdated software, saying last year,

the block that is coming off the line right now is not a block that I feel good about going up against China and Russia.

He noted recent war games focused on the prospect of defending Taiwan from Chinese air attack showed

Every [F-35] that rolls off the line today is a fighter that we wouldn’t even bother putting into these scenarios.

This means Australia’s F-35s appear not to be as good as the potential opposition. It seems Australia is paying to lose the air combat battle.

The only solution: another upgrade

So, what is the solution to these seemingly intractable and eye-wateringly expensive problems?

Lockheed Martin is advocating a major operating system software upgrade: the Block 4. It might not be surprising to hear this is now running years late, with delivery expected in 2027 or later. It is also significantly over budget.

In a small piece of good news, the last nine F-35 aircraft Australia will get off the production line next year, and may be partly Block 4 compatible. Hinote thinks these F-35s might be capable of fighting against first-rate adversaries.

Read more: With China-US tensions on the rise, does Australia need a new defence strategy?

The bad news is the full Block 4 upgrade now requires a major engine upgrade or even a new engine. So, this means Australia’s current F-35 fleet might not be able to use all the Block 4 software until after 2030 – and at a substantial cost.

Buying another hugely expensive upgrade for a brand new fighter is actually the cheap way out. The US Air Force’s focus is already shifting to the Block 4 upgraded aircraft. Countries like ours with older F-35s will be left to fend for ourselves if we don’t embrace the new technology, as well.

But the costs do keeping going up, and the problems with these F-35 jets haven’t seemed to stop. It’s the price of buying off the plan, which anyone who’s bought a house or apartment would surely know.

Authors: Peter Layton, Visiting Fellow Griffith Asia Institute, Griffith University

Read more https://theconversation.com/australia-spent-billions-on-jet-fighters-off-the-plan-now-were-having-trouble-even-flying-them-177156

Business News

How Businesses Can Prepare for Unexpected Power Outages

Power failures can occur quickly. The supply may be interrupted by bad weather, issues with the electricity network, damaged equipment or local construction work. This can be just a hassle for a fam...

Daily Bulletin - avatar Daily Bulletin

How Chatswood Tutoring Can Fit Into a Student’s Weekly Routine

Create a Predictable Weekly Structure A consistent weekly routine can make study easier to manage when students are balancing several subjects. Chatswood tutoring can provide a fixed learning point a...

Daily Bulletin - avatar Daily Bulletin

The Rise of Digital Marketplaces in the Australian Trade Sector

For decades, the Australian trade and construction sector operated almost entirely on word-of-mouth recommendations and local community networks. Small business owners typically relied on local newspa...

Daily Bulletin - avatar Daily Bulletin

How Immigration Lawyers Can Help

Introduction Visa decisions can shape employment, family life, study plans, travel, and future residence. A small omission can lead to delay, added expense, or refusal. Immigration lawyers assess l...

Daily Bulletin - avatar Daily Bulletin

How Industrial Drying Equipment Supports Efficient Processing

Many industrial processes require moisture to be removed from compressed air, products or process materials before they move to the next stage. Excess moisture can affect equipment performance, produc...

Daily Bulletin - avatar Daily Bulletin

Practical Ways a Whiteboard Can Improve Workplace Communication

Effective communication helps teams stay organised, share ideas and keep track of important information. While digital tools are now common in many workplaces, a whiteboard continues to provide a simp...

Daily Bulletin - avatar Daily Bulletin

Designing Eco-Friendly Custom Water Bottles for Your Next Event

The Evolution of Sustainable Event Merchandise Event planning has undergone a massive transformation over the last decade. Gone are the days when organizers could hand out cheap, single use plastic...

Daily Bulletin - avatar Daily Bulletin

Why Choosing a Professional Florist Melbourne Makes Flower Delivery Impactful

Flowers have a great power to speak when humans cannot express their feelings with right words. Flowers are the best gifts when you are celebrating a birthday or welcoming a newborn child into your fa...

Daily Bulletin - avatar Daily Bulletin

The Business Case for Choosing Australian Fabricators Over Imported Alternatives

For a long time, you might have defaulted to overseas suppliers when sourcing fabricated metal components for a project. The unit price was lower on paper, and the maths seemed straightforward. That...

Daily Bulletin - avatar Daily Bulletin

The Daily Magazine

Why Preventive Care Matters for Heavy-Duty Equipment

Heavy duty equipment is supposed to operate under the same conditions as a normal machine but do s...

7 Natural Tips to Restore Shine and Softness to Dull Hair

Healthy, lustrous hair often feels like an unattainable dream when you are dealing with dry, brittle...

Buying Property with Someone else? Settle these Questions First

Buying a home with a partner, a sibling or a friend can make a purchase possible that neither of you...

How to Handle a Blocked Drain in Bribie Island Before Starting Deck Repairs

Planning an outdoor upgrade brings excitement, but building a beautiful timber deck requires caref...

What to Look For When Selecting an Installation Specialist for Gas Stoves and Water Filters in Brisbane

Upgrading your kitchen or improving your home's water quality requires specialised skills. When mana...

What to Consider Before Cleaning Your Exterior: Deck Pressure Cleaning, Pressure Cleaning, and How Much Does It Cost to Pressure Wash a House?

Maintaining a home's exterior in coastal Sydney requires regular attention to combat salt spray, mou...

Signs Your Trailer Needs Professional Repair Before Its Next Long Haul

A long road trip can put considerable strain on a trailer, particularly when it is carrying heavy ...

Automatic, Manual, CVT or DCT: Which Transmission Suits Australian Drivers?

Australia’s enthusiasm for cars is nothing new. From family SUVs and work utes to compact city cars ...

Cape Town: Full Day Private Cape Peninsula & Cape Point Tour

Embark on an unforgettable adventure with a full day private Cape Peninsula & Cape Point tour...